SAP System Vendor Project Success Criteria & Factors 5 Posted: 29 Nov 2010 05:14 AM PST This is the final post in the series on SAP project shared success criteria. Doing this entire topic justice has been more of a challenge than I had originally anticipated and at some point I will put it all together in a PDF e-book. This series leaves you with a lot to digest but over the years these items generally make up the foundations for a very successful project that is able to transform your business. This series has been challenging but interesting and I am glad it is complete. In a few more weeks I will be coming back around to try to wrap up my series on SAP reimplementation for little more cost than a technical upgrade. That one turned out to be more challenging than I had originally expected. Until then, here is the final installment in this series on project success criteria.
Legend A = Primary Responsibility for the success factor 21. SAP Data Analysis and ConversionOne of the major activities of an SAP project is the data analysis and conversion. On many projects there are too many new data requirements or data changes needed after the system goes live. One way to avoid so many of the data correction in a live production system is to ensure that you have sufficient integration and cutover testing. We will look at testing in a moment. The primary responsibility for data conversion is generally on the customer. Customer primary responsibilities include:
I've developed a short list of the common data conversion risks as adapted from the SAP ASAP 7.0 Data Migration and Risk Assessment Template. That template, provided by SAP, contains a sample issue and risk log, and includes some suggestions on how to manage the following common data conversion risks: SAP Data Conversion Project Management Risks
SAP Data Technical Conversion Risks
Preparing conversion programs, or more specifically, using SAP's variety of conversion tools and resources is a vendor responsibility. Together with that the vendor, who has set up the system with the master data requirements is also responsible for providing data load templates as well. Further the vendor's functional consultants must participate in the data conversion design and development activities because they are the ones that set up the system and know the master data requirements better than anyone. The only exception to this is if you decide to bring in consultants who do knowledge transfer to your implementation team and your own internal team does all of the system setup. For an overview of the various data transformation methods in an SAP project please see the following post: Planning For a Smooth SAP Go-Live: Part 2 SAP Blueprint Master Data RequirementsAs a final note, a system integrator should be able to provide a first pass at basic master data requirements by the end of the Blueprint phase. In fact your SAP Blueprint should contain a technical blueprint section with significant amounts of detail.
If your SAP system integrator Blueprint does NOT have this level of detail then it is not sufficient to set up the system and perform the necessary master data conversion. Further, if it lacks this level of detail you may want to fire your system integrator and demand a refund of at least part of what they bill. By having this level of detail at the end of SAP blueprinting (process details, master data details, interface requirements, forms, reports, etc.) you can immediately move into setting up the system. If you lack this level of detail you may find yourself forever in design mode (revisiting normal blueprint requirements) and blowing both the budget and the timeline. I suggest you add this summary of the type of detail you want by the end of the blueprint phase to your contract. 22. SAP Test PlanningYou will have to determine who needs to perform what testing, when, and where. Together with that you will also want to use this as an opportunity to get both "power users" and non power users involved in the testing. This becomes the early part of knowledge transfer as well as user acceptance testing. Inevitably the additional resources from outside of the project team will discover gaps or items that might need to be addressed. The Test Planning responsibility is primarily on you as the SAP customer. Your primary goal here is to ensure that every process you put in scope is represented in some type of testing script. For example, in your order to cash process you might want test scenarios that include credit processing with and without product returns; third party drop shipping to the customer direct from the vendor; pro-forma invoice processing and then follow-up commercial invoice processing; interfaces to and from various external systems; online order entry processing with and without manual intervention; backorder processing and sourcing from other facilities, etc. At a high level you will be responsible for ensuring that you cover all of the key processes that need to be tested. SAP Test Strategy and Testing Approach
Change Control Process (for an overview and details of the SAP change control process see SAP System Integrator Shared Success Criteria Evaluation 4 which focuses critical success factor on #20 on this list of "System Change Control Process"). As for a test script, I have included an example one which is a modified version of the standard options SAP provides as part of the older ASAP methodology. EXAMPLE SAP TEST SCRIPT with Ad Hoc or Variant Section information. 23. SAP Test DevelopmentAs for test development this is clearly a vendor primary responsibility. Unless you use SAP's integrated Solution Manager resources for testing this is probably one of the areas where you will have to rely heavily on your SAP partner. The reason this is primarily a vendor responsibility is that as an SAP customer "you don't know what you don't know." Unless you have adopted an approach where you require the implementation vendor to act as pure consultants, where your own project team does all of the system setup, you will not know the detailed testing requirements. As a result a vendor must be able to walk you through the transaction strings and dependencies. They must be able to take the entire process-related solution they blueprinted from master data creation through cash processing and any interfaces or manual steps in between. Because of time, budget, and limitless possibilities there is only so much testing in a project. These limitations create a requirement that only a "limited universe" of testing can be accomplished and SAP system integrators will usually require someone to sign off on those limited tests. There are a few things to beware of here: 1) When the tests have been "gamed" to support only a successful outcome and not to actually test the solution. 2) When a system integrator pushes back on testing variations that they may not have documented in the "formal" test scripts. 3) Any vendors who engage in hard push back against additional ad hoc, variant, or converted data testing. Unfortunately I have seen a couple of the major SAP system integrators KNOWINGLY push trash on their customers. For a thorough testing program you should always ensure your tests include any of the custom development objects as well as manual processing steps. For example, a thorough test process must include testing of any outputs (forms), interfaces, enhancements, and reports. Data conversions should also be tested but may be done separately. However, one strong word of caution here, once converted data is available, even if you do not do formal testing, be absolutely certain to do as much process testing as possible with the converted data. Testing with converted data will reveal a number of potential problems that can be corrected or resolved before you go live. ============================== For help with a successful SAP project contact us today. What have you got to lose in making the call or writing? Bill Wood For an overview of some of our services, whether it is SAP staff augmentation, SAP project assessments / audits, at-risk project interventions, or several other areas we might help then please see our service page ( http://www.r3now.com/services ). If you have any other questions please visit our contact page ( http://www.r3now.com/contact ) for more information. ============================== Related Posts: |