| SAP System Integrator Shared Success Criteria Evaluation 4 Posted: 22 Nov 2010 05:09 AM PST
Many of the steps, insight, techniques, and other suggestions I have made were gleaned from the SAP ASAP methodology and my experience with the various toolsets SAP provides to their customers and vendors. This post will address this SAP or ERP critical success factor about the SAP System Change Control Process from my experiences on SAP projects since 1994.
Legend A = Primary Responsibility for the success factor 20. SAP System Change Control ProcessWhen it comes to SAP system changes the software is pretty mature. Between the SAP Correction and Transport System (CTS) and more recently the Solution Manager options, SAP change control options are very robust. Because the landscape approach is mature, and because SAP provides most of the change tools for success I have placed this item 100% under SAP system integrator responsibility. For the actual management of the system changes themselves, including gateway approval processes for moving changes an SAP system integrator should have proven tools and methods for managing this entire process. What is critical for you as an SAP customer, or prospective customer, is to ask SAP system integrators for samples of their change control processes and their spreadsheets, approval templates, or other resources for managing SAP system changes. Some Steps and Considerations to Defining an SAP System Change Control Process
Poor SAP Change Control Processes Can Create Major ProblemsIn spite of the normal three (3) tier system landscape SAP has proposed for years (Development – QA / Test / Training – Production) I'm still amazed by how many times production systems are opened up for direct changes. With very few exceptions (and there are a few, like number range changes) any developer or consultant who insists on a need to open the production system may need to be removed from the project. This is very high risk and can cause the system landscape to be out of sync. Any supposedly "experienced" consultant who does not understand the need to follow a properly defined change control and verification process should not be on an SAP project or near any business technology system.
Making direct production system changes creates inconsistencies in the SAP system landscape which:
For example you may test something in your QA system and then when you move the change to a production system that has been changed independently your production system may fail. And that is just one example. Once the damage is done it may be difficult to make the landscape consistent. Sometimes it may not be possible to make the SAP landscape consistent at all depending on the types and quantities of changes. The first step to a good change management program is the system landscape itself. This diagram shows a typical "best practice" system landscape and the transport paths. Or how the SAP CTS (Correction and Transport System) should be set up to move changes. SAP Landscape Configuration Assumptions / DecisionsAn SAP system landscape has a 'Configuration Master' client on the Development box. This SAP Development Master Client contains only system changes and custom programs. There will generally not be any master data there except the few items that are needed to directly support the system setup. The SAP Development landscape change process has an SAP Development Sandbox for prototyping, concept checking, or testing various methods on setting up transaction processing. The initial prototyping and concept checking in the SAP Sandbox will not be directly transported. Once SAP configuration is (1) set up in the Sandbox and appears to meet the requirement it is (2) set up again in the SAP Development Test System to ensure that it works as expected (the Dev Test system is generally a much "cleaner" system than the Sandbox). After satisfactory results in the SAP Development Test System the changes are recorded in the test system and then (2) copied to the data conversion and ABAP programming client. This is a parallel activity to the SAP configuration activities taking place in the Dev Test environment. ABAP programming is generally considered "client independent" which means that any code that is created is automatically generated in all of the associated clients. This is why it is generally a separate client that has a separate transport path. As ABAP coding or data conversions are completed enough to test, the underlying code is used to generate a transport request that is then (3) copied into the SAP Development Master Client. When this code is copied into the Master Client it is automatically generated in the other clients in that landscape as well. From there the coding can be tested and verified in the Dev Test client even though that transport was not copied into there. As the SAP configuration and SAP ABAP development-conversion activities are completed and then copied into the SAP Development Master Client, they are then (4) moved into the SAP QA (Quality Assurance) Test system. At a pre-defined point in your SAP project, a Training client is created from the SAP QA Test System. Once that Training Client is created and the training data and training documentation is created you will not generally move any new configuration or coding changes into that system unless they are critically needed. The reason you stop SAP Training Client changes is that even if the training environment is not 100% perfect (generally +90% is sufficient), you need a stable environment to create your training data and documentation from. As necessary you will create additional training clients as part of your overall training strategy. For more information on the various types of training throughout your SAP project lifecycle please see Change Management Strategies and Knowledge Transfer Processes for a Successful SAP Project 1 and the second part at Change Management Strategies and Knowledge Transfer Processes for a Successful SAP Project 2 . Once the SAP QA testing is successfully completed you will manually (5) move each of the QA CTS (Correction and Transport System) objects into the SAP Production System and into the SAP Pre-Production client [FN1]. You begin the process from the beginning if there are any adjustments, changes, or corrections needed during the SAP QA testing process. Once you are satisfied with the testing results, and the changes or corrections have been moved into the production system, you perform your mock go-live or mock conversions in the live production system or in the pre-production system (depending on your landscape design). Conclusion on SAP Configuration, Correction, and Change Management ProcessesOver the years I've seen some well done, carefully controlled, and well managed system landscapes. The one thing that set them apart was how they managed the system change process. SAP itself provides a significant number of tools and resources, including BC Sets (Business Configuration Sets) which we don't have time to address today. However the important thing to understand is that a properly constructed system landscape and change process is critical to a successful SAP implementation. On the other hand I have come onto other SAP sites at customers where their system integrator should have been sued into non-existence. SAP is not some new and unproven software application with weird new ways people are experimenting on implementing it. But like my friend and previous co-worker Michael Doane says (paraphrased) it is still shocking at the number of SAP implementations that are done as if the application just came out yesterday and people are trying to figure out how to implement it. Do not underestimate the importance of a well thought out and carefully controlled SAP system landscape and change control process. In the end it can mean the difference between a smooth go-live with relatively few bumps (when taken in context with all of the other critical success criteria) and a complete disaster ====================== [FN1] My personal experience as a "best practice" is that you are better to have a separate pre-production client available to do your Mock Go-Live testing in. There are several reasons an SAP pre-production client is useful: you can quickly simulate live production processing; if significant data changes are discovered at the last minute that can be remedied in the pre-production system with some of the mass change tools or other correction methods you can easily ALE (Application Link Enabling) the master data from one client directly into the live production client. This provides another risk mitigation point for the live conversion. ============================== For help with a successful SAP project contact us today. What have you got to lose in making the call or writing? Bill Wood For an overview of some of our services, whether it is SAP staff augmentation, SAP project assessments / audits, at-risk project interventions, or several other areas we might help then please see our service page ( http://www.r3now.com/services ). If you have any other questions please visit our contact page ( http://www.r3now.com/contact ) for more information. ============================== Related Posts: |